Welcome to the 221st Pari Passu Edition.

Millions of commuters have passed through fare systems built by Cubic Corporation without ever knowing its name. For decades, the company has designed, built, and operated transit systems in New York, London, San Francisco, and Sydney, alongside a defense business that trains fighter pilots and keeps military forces connected in the field. In 2021, Veritas Capital and Elliott's Evergreen Coast Capital took Cubic private for roughly $3.0bn. The business they acquired, however, depended on large, fixed-price contracts that earned thin margins during construction and much more once systems moved into operation. When those builds ran late and over budget, Cubic was left funding the work while waiting on payments from transit agencies, driving much of its financial trouble over the next five years.

Cubic has since completed two out-of-court restructurings in little more than a year. In July 2025, it exchanged its debt into a three-tier superpriority structure that reduced claims, brought in new sponsor equity, and extended maturities into 2029. The legacy first-lien lenders took second-out paper, and the loans rallied into the low 70s on the announcement. Within six months, Cubic was missing coupons, and within a year the same loans were quoted below 10c. In September 2026, a second amendment added debt ahead of existing lenders and converted all cash interest to PIK. Very few companies start negotiating a second restructuring within months after the first, and even fewer see such deep impairment in the BSL market. Unlike some of our recent coverage, Cubic's problems extended well beyond its capital structure. 

In today's writeup, we'll start with Cubic's transportation and defense businesses. We'll then cover its corporate history and the bidding war preceding the 2021 buyout. From there, we'll trace the delayed projects, cost overruns, and liquidity problems that drove Cubic into distress. We'll break down the July 2025 exchange, why it proved insufficient, and the September 2026 amendment that followed. Finally, we'll examine what the two transactions mean for creditors and what next steps may look like for Cubic.

The connector for credit

Query 9fin’s proprietary credit data, covenants and analysis directly from Claude, ChatGPT or Copilot. Our MCP server delivers source-cited answers in the AI tools your team uses.

Move from question to credit decision in seconds.

Business Model 

A commuter taps a card at a subway gate and walks through in well under a second. Behind that tap, a system must determine the correct fare, account for transfers and discounts, process payment, and reconcile proceeds across operators. Now multiply that single tap across millions of riders a day, hundreds of stations, and thousands of vehicles. The system also has to work even when devices lose connectivity. Transit agencies almost never build this machinery themselves. Instead, they hire a specialist to design, install, and often run it for a decade or more, and Cubic has been one of those specialists since it built the magnetic stripe fare system for the New York City subway [1]. 

Headquartered in San Diego, Cubic operates two largely separate businesses: Cubic Transportation Systems (CTS), which builds and operates fare collection and traffic systems for transit agencies, and Cubic Mission & Performance Solutions (CMPS), which sells training, communications, and intelligence technology to the US military and allied forces [1]. Both sell to public bodies through long procurement cycles. In fiscal 2020, the last full year Cubic reported as a public company, transportation generated roughly 57% of its approximately $1.5bn of revenue, with defense accounting for the remaining 43%. About 95% of that revenue came from fixed-price contracts, under which Cubic agrees to deliver a system for a set amount [2]. A typical transit contract runs in two phases: multi-year design and build, followed by a long operate-and-maintain (O&M) phase that generates recurring service fees. The economics of the two phases differ sharply. The build carries thin margins, with much of the contract value going to hardware, installation, and engineering, while O&M earns recurring fees on a system already in place at much higher margins. A contractor’s earnings therefore depend on moving its builds into operation. 

Cubic Transportation Systems:

A fare collection system has three layers. At the edge are the gates, bus card readers, and ticket vending machines. Behind them sits the software that calculates fares, manages rider accounts, processes payments, and settles money between operators. The third layer is the ongoing maintenance and customer service needed to keep the network running. Cubic sells all three as a single integrated system [1]. 

The architecture of these systems has changed over time. Older systems such as London's Oyster card, which Cubic built, store value on the card itself, with readers calculating and deducting fares locally. Newer systems hold rider accounts centrally, calculating fares after each journey rather than at the gate. Because the central system does the thinking, riders can use their own bank cards, phones or smartwatches instead of dedicated transit cards. The industry calls this account-based ticketing, with bank card acceptance known as open payments. Cubic helped pioneer contactless bank card payment on London's network and has carried the approach into its other large systems [1]. 

Those systems include some of the largest transit networks in the world. In New York, Cubic runs OMNY, the tap-to-pay system that replaced the MetroCard, under a contract with the Metropolitan Transportation Authority that runs through 2030, with options to 2040. Its other systems include Clipper in San Francisco, Ventra in Chicago, and fare systems in Boston, Vancouver and Sydney. In New Zealand, it is building a national ticketing system spanning buses, trains and ferries [1]. 

Figure 1: Cubic’s OMNY tap-to-pay system 

Smaller transit agencies cannot afford a custom system of this scale, so Cubic also sells Umo, a cloud-hosted platform that an agency subscribes to rather than builds. Umo offers bank card acceptance, transfers and fare caps, with one version allowing riders to scan QR codes instead of using onboard fare collection hardware. CTS also manages road traffic. Its Gridsmart cameras monitor intersections, while Trafficware controllers and software adjust traffic signals. It also runs highway incident monitoring for Transport Scotland [1]. 

Cubic Mission & Performance Solutions:

Cubic formed CMPS in 2020 by combining two earlier defense units into one segment. The oldest piece of the business is combat training. Its aircraft-mounted pods track fighter jets during exercises, simulate weapons fire, and score engagements for debriefing. Cubic built the original version of this kind of system behind the Navy's "Top Gun" training, and its current P5 system is installed at more than 30 ranges worldwide. It also supplies F-35 training technology through Lockheed Martin and ground-based systems that simulate combat for infantry and vehicles. These products are part of live, virtual, and constructive (LVC) training, which blends real exercises, simulators, and computer-generated opponents [1]. 

The second half of CMPS keeps forces connected in places without reliable networks. Its DTECH line packs servers, routers, and processing power into ruggedized cases that troops carry to forward positions, so data can be processed in the field rather than sent back to a base. Its GATR antennas inflate into satellite dishes light enough to carry by hand. For the US Marine Corps, Cubic supplies troposcatter systems that communicate beyond the horizon without satellites. Alongside the hardware, Cubic sells software that combines drone video, maps, and sensor feeds for battlefield commanders [1].

Both businesses also rely on letters of credit (L/Cs), which transit agencies and defense customers often require as guarantees that Cubic will fulfill its contracts. An L/C is a bank's promise to pay the customer if Cubic fails to meet certain obligations. Cubic pays a fee to keep the letter outstanding and must reimburse the bank if it is drawn. These guarantees are issued through committed L/C facilities, which banks secure either with restricted cash or claims on Cubic's assets. Cubic has used both arrangements over time. Because customers often require these guarantees before awarding contracts, maintaining sufficient L/C capacity is an important part of Cubic's business.

Within fare collection, Cubic competes against a small group of global integrators, including Conduent, Scheidt & Bachmann, Indra, Vix Technology and INIT [1]. Cubic's niche is the largest and most complex networks, where a decades-long operating history and the ability to integrate multiple operators carry the most weight. Those rivals, however, have become increasingly competitive for large contracts, as we will explore later in this edition [3]. Among mid-sized agencies, competition increasingly comes from cloud software providers such as Masabi and Flowbird, which are moving beyond subcontracting to bid directly for transit contracts. Cubic competes in this market through Umo. On the defense side, CMPS operates across many niche product lines and faces a long list of specialized competitors, with its strongest position in air combat training instrumentation [1]. 

The global fare collection market is worth roughly $15bn and is expected to grow at a low double-digit rate through the end of the decade [4]. Most of that growth comes from software rather than hardware. As agencies adopt open payments, riders bring their own cards and phones, reducing reliance on specialized fare collection hardware. That shift lowers the cost of entry for software-only vendors and pressures incumbents when contracts come up for rebid. Defense demand is more dependent on government budgets and procurement priorities, including a recent US Army reorganization that shifted funding across programs [5]. 

Corporate History 

Walter Zable founded Cubic in a San Diego storefront in 1951, initially producing equipment to test microwave output. Defense electronics carried the company through its first two decades. In 1973, Cubic delivered the first air combat training range to the Marine Corps at Yuma, the system later popularized by "Top Gun" [6]. Fare collection entered the picture in 1972, when Zable bought Western Data Products, a struggling manufacturer of rail fare equipment, and later acquired technology IBM had abandoned at a discount. Cubic began supplying ticketing equipment to San Francisco's Bay Area Rapid Transit that same year and entered the London Underground in 1985, establishing two of its longest-running transit relationships [6]. Cubic went public in 1959, and remained a public company for more than six decades, until the 2021 buyout that would change its trajectory. Zable retained nearly 40% of the company and remained CEO until his passing in 2012 at age 97 [7]. 

Bradley Feldmann, a longtime Cubic defense executive, became CEO in 2014 and spent the next six years reshaping the portfolio [6]. In 2018, Cubic sold its defense services arm, which provided exercise support rather than proprietary technology, to Valiant Integrated Services for $135mm in cash [8]. Next came a run of acquisitions. Between 2015 and 2019, Cubic acquired DTECH, GATR, TeraLogics, MotionDSP, Vocality, Shield Aviation and Nuvotronics to expand its defense communications and intelligence business [9]. On the transit side, it bought Trafficware for approximately $237mm and GRIDSMART for approximately $87mm in fiscal 2019, adding the traffic management products we described earlier. Cubic also acquired imagery software provider Pixia in two steps between June 2019 and January 2020 for approximately $245mm. In 2020, Cubic folded its two defense units into the single CMPS segment, which gave the company the two-segment shape it has today [6].

In September 2020, Elliott Investment Management disclosed a stake of roughly 15% and expressed interest in buying the company, prompting Cubic's board to adopt a poison pill to deter an unsolicited takeover (a poison pill gives existing shareholders the right to buy discounted shares if an investor crosses a set ownership threshold, diluting that investor's stake and making a takeover more expensive) [6]. By February 8, 2021, the board had agreed to sell Cubic to Veritas Capital and Evergreen Coast Capital (Elliott's private equity affiliate) for $70 per share. That price was a 58% premium to Cubic's share price before the interest became public and valued the company at approximately $2.8bn. Then ST Engineering, the Singaporean defense group, made an unsolicited counterbid. It planned to keep the transit business and sell the defense business to Blackstone. Veritas and Evergreen raised their offer to $72 per share, ST Engineering countered at $78, and the sponsors came back at $75. Cubic's board accepted the lower $75 bid on March 31, citing the greater certainty and speed of closing with the existing buyers [10]. Shareholders approved the amended deal on April 27, and it closed on May 25, 2021, at a value of approximately $3.0bn. The bidding war had raised the sponsors' price by $5 per share, or roughly 7%, before the buyout financing was put in place.

Path to Distress

Veritas and Evergreen financed Cubic's $3.0bn buyout with a $1,475mm first lien term loan B and a $300mm first lien term loan C, both due May 2028, along with a $325mm second lien term loan due a year later [11]. An undrawn $225mm revolving credit facility due May 2026 sat alongside. The TLC was unusual. Cubic held its proceeds as restricted cash backing a separate letter of credit facility, which supported performance guarantees required by transit agencies and defense customers [12]. The $300mm was therefore counted as funded debt but was unavailable to finance the acquisition. With $2.1bn of total debt, only $1.8bn went towards financing the acquisition, which, in our view, likely meant an equity check near $1.3bn. Lenders underwrote the structure against approximately $337mm of credit agreement EBITDA, implying first lien leverage of roughly 5.3x and total leverage of 6.2x. On actual earnings, the picture looked very different. Cubic had guided to $170–190mm of adjusted EBITDA for fiscal 2021 [2], so the marketed EBITDA was nearly 90% higher than the company’s own guidance. At the $180mm midpoint, first lien leverage was roughly 10x and total leverage roughly 12x. The gap likely reflected an underwriting case that relied heavily on cost savings, run-rate adjustments and expected earnings from transit contracts, and market participants described the leverage as extremely high from the outset. 

Figure 2: The 2021 Buyout; assumes $100mm unrestricted cash to balance sheet

However, there is an argument for the structure. Fare systems run under contracts that span a decade or more, and replacing one means migrating millions of riders, every gate and validator, and the back office that settles fares across operators. Swapping out the system behind OMNY would be a multi-year undertaking for the MTA, which is why incumbents like Cubic have historically held on to these contracts. Even so, roughly 10-12x on actual earnings made for a very aggressive entry capital structure, with little room for the operational problems that would soon follow. 

Cubic's ability to service its debt depended heavily on its large transit projects finishing on time and on budget. The build phase of each contract earned thin margins, and much of the EBITDA in the underwriting case depended on those systems reaching the higher-margin O&M phase. Cash lagged in the same way, since agencies pay much of the bill once a system is running, with the difference accumulating as contract assets on the balance sheet [6]. The plan depended on that transition, and it stayed the base case well after the buyout. As late as mid-2023, S&P still expected positive free cash flow of roughly $35mm in 2025 and $50mm in 2026 and 2027, as four large legacy contracts moved into operation [13]. Those projects also needed to stay on budget, as fixed-price contracts left Cubic responsible for cost overruns [6]. 

Operational Distress:

Operating problems emerged within a year of closing. In the quarter ended June 30, 2022, revenue fell 9% year over year to $320mm and adj. EBITDA fell roughly 13% to $65mm. Management blamed shipping and component shortages, along with lower revenue on certain contracts [11]. For a fixed-price integrator, delays mean continued engineering costs while project milestones and associated cash collections are pushed back. By late 2022, free cash flow and credit metrics were well below expectations set at the buyout, and municipal contract startups were progressing slower than planned. By March 2023, revenue was down roughly 8% since the LBO and credit agreement EBITDA was down roughly 13%, while S&P's leverage figure had climbed from roughly 10x at close to roughly 15x [13].

The fixed-price problem compounded from there. The flagship builds in New York, Boston, and San Francisco ran over on both time and cost, and Cubic had to renegotiate its Boston contract [14]. In New York, the MTA pared back Cubic's role on OMNY, removing the commuter rail rollout and handing the ticket vending machine build to Scheidt & Bachmann, with Cubic refunding $36mm [3]. The MTA later reported that program costs had risen roughly $200mm against the original 2017 budget [15]. By June 2024, quarterly revenue had fallen 26% year over year to $289mm, while adjusted EBITDA dropped to $53mm [16]. 

The clearest measure of how far the business had drifted came at the end of 2024. Cubic reported Dec’24 LTM adj. EBITDA of $295mm, while its cash EBITDA for the same period was roughly negative $6mm [17]. The gap likely reflects how Cubic accounts for its contracts. Cubic books profit on design-and-build contracts as it incurs costs, while customers pay on milestones [9]. Earnings can therefore arrive well ahead of cash, and delays can widen the gap, as Cubic keeps booking progress on builds stuck in their low-margin phase while collections tied to completing them keep moving out. Meanwhile, cost overruns continued to consume cash. Contrary to agency projections, cash burn had exceeded $100mm in each year since the buyout [14]. 

Cubic's liquidity steadily deteriorated as project delays and cost overruns continued to consume cash. In June 2022, Cubic held roughly $154mm of cash alongside its fully undrawn $225mm revolver, for total liquidity of $379mm [18]. By September 2024, liquidity had fallen to roughly $220mm, and by March 2025 it was down to just $110mm, comprising $40mm of cash and $70mm of remaining revolver capacity [19]. These figures exclude restricted cash backing the TLC. Cubic lost roughly $110mm of liquidity between September 2024 and March 2025, averaging $55mm per quarter. At that pace, the remaining $110mm provided roughly two quarters of runway, putting Cubic on track to exhaust its liquidity in the second half of 2025. The revolver did not mature until May 2026, leaving Cubic facing a liquidity crisis well before its first debt maturity.

The Market’s Reaction:

The term loans reflected Cubic's deteriorating outlook. The first lien initially traded in the mid-90s and was still around 95 in September 2022, but had fallen to the mid-60s by March 2025 [11] [17]. By June 2025, with an LME increasingly expected, prices had fallen as low as 48 [15]. With the 1L trading at less than half of face value, both the 2L and the sponsors’ equity were clearly out of the money. 

By March 2025, Cubic had retained PJT Partners as financial advisor and Kirkland & Ellis as legal counsel. Senior lenders organized around Davis Polk and Centerview, while a separate group of junior lenders retained Evercore [17]. The stage was set for a (first) LME.

You are about to reach the midpoint of the report. This is where the story gets interesting.

Free readers miss out on the sections that explain:
• 2025 LME Economics
• The London Contract
• Missed Coupons
• Restructuring Round #2
• Transaction Analysis
• Key Takeaways

Upgrade to Pari Passu Premium to access the remainder of this deep-dive, the full archive with over 200 editions, and our restructuring drive.

Professionals accessing Pari Passu in connection with their work at a financial institution, investment firm, law firm, consulting firm, or any other commercial enterprise are required to upgrade to the Research Tier.

All subscriptions are licensed for a single user. No subscription, at any tier, may be shared, forwarded, or made accessible to other employees, colleagues, or a shared/group inbox. Firms with multiple users must obtain a group subscription. To set up group access for your team, please contact [email protected]

Our LME Tracker is reserved for group subscriptions

logo

Unlock the Full Analysis and Proprietary Insights

A Pari Passu Premium subscription provides unrestricted access to this report and our comprehensive library of institutional-grade research

Upgrade Now

Already a subscriber? Sign in

A subscription gets you:

  • Institutional Level Coverage of Restructuring Deals
  • Full Access to Our Entire Archive
  • 200+ Reports of Evergreen Research
  • Full Access to All New Research
  • Access to the Restructuring Drive
  • Join Thousands of Professional Readers

Keep Reading

View more